Do you need council approval for a shed in Tasmania?
Get a Quote
A shed in Tasmania may need planning approval, building approval, both, or neither. It all depends on things like the size of the shed to be erected, its position on the block, and the zoning and overlays that apply to the property. This is where council approval for a shed in Tasmania can get confusing, as there are two different sets of rules to consider, but they are often treated as though they are the same thing.
Here, we explain which approval you might need and what happens if a permit is required. It also covers how to check the requirements for your own land before you get too far into the project. Fair Dinkum Builds designs engineered, code-compliant steel sheds, which takes care of the building side from the start.
Do all sheds in Tasmania need council approval?
No. Most small sheds in Tasmania can be built without a permit. However, there are two distinct tests that the shed must pass, and the second is easy to overlook.
Planning is the first one. The planning authority for your area is the local council under the Tasmanian Planning Scheme. This scheme decides whether you can construct the shed on your land based on your property’s zoning and overlays.
The second test covers the building itself. Under the Building Act 2016, different types of building work have different requirements. Consumer, Building and Occupational Services (CBOS) groups that work by risk, and low risk work can usually be done without a building permit. Once you move into larger sheds, though, the process changes. You may need a building permit, or a building surveyor may need to assess and sign off the work.
Because the council examines the two systems individually, passing one of them does not mean that the other will be cleared automatically. Basically, you shouldn’t assume that there is no need for approval in the first place until you have checked both sides.
The thresholds in Tasmania are also specific to the state. If your land is elsewhere, check our guide to shed approval in other states, as the rules and limits change across state borders.
What size shed can I build without a permit in Tasmania?
A prefabricated shed up to 36m² can be put up without a building permit, whereas a shed that is constructed on-site may not exceed 18m². However, this is only the building aspect of things. There are planning limitations as well, and on residential land, they may be even lower. You should check all limitations before you order, rather than finding out afterwards that your shed needs approval.
Planning exemptions (residential and rural)
On residential land, the State Planning Provisions allow a small shed of up to 9m² gross floor area without a permit for planning. There are instances where that limit may go as far as 18 m2. However, in order to qualify for this, the shed should not have an existing outbuilding on the same piece of land, and it should be below 2.4 m high with a roof span of 3m or less. Also, it should be at least 0.9 m away from the boundaries and any existing building. Go beyond those limits on a residential block, and you will need a planning permit.
The limits are more generous in rural zones. In Rural Living, Rural and Agriculture zones, an outbuilding linked to an existing dwelling can be exempt when all outbuildings on the lot have a combined gross floor area of 108m² or less. The building must also meet the required setbacks, stay within 6m in height, and have walls no higher than 4m.
There is a separate exemption that applies to farm buildings used in connection with agricultural land use.
Building exemptions (low risk work)
Under the CBOS Director’s Determination, a shed, a garage, a carport or other similar outbuildings that are constructed on-site fall under Category 1 low risk work, provided they do not exceed 18m2. In the case of prefabricated sheds, the maximum area allowed is 36 m2. As long as you adhere to the above guidelines, you won’t need a building permit, a building surveyor or an owner-builder permit.
Just because you’re able to build without a building permit, it does not mean that there will be no paperwork at all. Once the shed is up, you still need to notify the council and ensure that the completed structure meets the standards of the National Construction Code. You also need to check the planning requirements separately.
Take a 30m² prefabricated shed on a standard residential block as an example. It can be exempt from a building permit, but it still needs a planning permit because it exceeds the 9m² or 18m² planning limit.
These facts are derived from the State Planning Provisions and CBOS Determinations as of the date of writing, and must be considered as general guidelines only. The rules can change, and different councils have their own specific guidelines. Make sure you’re sure what applies to your property before you commit to the project.
Planning approval vs building approval: the two-system trap
Planning approval and building approval relate to different stages in the project. Being granted one does not automatically mean the other is approved. It is a simple difference, but knowing it up front can save Tasmanian shed buyers from an unwelcome surprise later.
Planning deals with the land and where the shed can go. The council will examine these aspects in line with the Tasmanian Planning Scheme, including zoning, setbacks, height restrictions, and permitted land use, along with any overlay that affects the site.
Building rules refer to the structure itself. According to the Building Act 2016, the local council or a private building surveyor inspects the structure and ensures its safety in line with the National Construction Code.
Neither automatically leads to the other. A prefabricated shed covering 30m², for example, could be exempt from a building permit but will still need planning permission to be built on a residential property. The opposite could happen in the case of a large farm shed, which could meet the rural planning exemption but still need a building surveyor due to its size. That’s why you should always check both before moving ahead.
Plumbing approval is another separate approval. If you are installing a tap or stormwater connection to your shed, that goes through the council as its own process.
Open-sided buildings also have the same separation between planning and building, but with different criteria. We discuss those in our guide to carport approval in Tasmania.
When a shed needs approval anyway: overlays, boundaries and rural blocks
Any shed, even one that fits inside the regular size limits, could require approval because of where you plan to put it. Boundaries and overlays can affect what is allowed, while the type of land you are building on can change the rules, too.
Bushfire, flood and heritage overlays
Bushfire-prone land is one of the most common triggers in Tasmania. If a bushfire overlay applies, the Bushfire-Prone Areas Code comes into play. Depending on the site, the building may need a Bushfire Attack Level (BAL) assessment and may have to meet AS 3959 construction requirements.
There is an exemption that can make a big difference to the cost. A detached, non-habitable Class 10a shed positioned at least 6 m from a habitable building does not have to meet those bushfire construction requirements.
A flood or coastal inundation overlay can take away the usual planning exemption. This means the shed will be subjected to an assessment with further restrictions on its location and floor levels.
Heritage restrictions go further. If your land is covered by the Local Historic Heritage Code, the exemption that is normally available for sheds under the State Planning Provisions will not apply. This means that a planning permit will be needed, regardless of the size of the shed. If you are going to use the shed as your home, this becomes something else entirely because it falls into another building class. Our liveable shed range covers that option.
Boundary setbacks and rural sheds
Setbacks from boundaries and the building line can determine whether or not your shed is exempt from permits. If you put it near fences or right in front of your house, you might find that you need a permit. Our guide to how close to the boundary a shed can go explains the limits in more detail.
A rural property is considered separately under both of these systems. In terms of planning requirements, a total outbuilding area up to 108m² is allowable without obtaining a permit. As far as building regulations are concerned, there is a different threshold: a prefabricated farm shed under 200m² is classed as low risk work and can be erected yourself. Once you go over 200m², a building surveyor needs to be involved.
Size is not the only consideration. The structure still has to be certified for the wind classification of your site. Tasmania is in Wind Region A, but the rating for an exposed hilltop can be quite different from one on a sheltered valley floor.
What to do if your shed needs approval in Tasmania
Low risk (Category 1) building work does not need a building permit. Once the shed is complete, you notify your local council using Form 80, the Notice of Low Risk Work. You'll need to attach a site plan and the engineer's plans. Make sure the planning side is sorted before you begin construction, though. Form 80 only deals with the building requirements.
For larger sheds over 36m², or for farm sheds over 200m², you can still avoid a full building permit in most cases. But you will need a licensed builder and a building surveyor.
The surveyor assesses the engineer’s plan and issues a certificate of likely compliance. They also notify the council before any building work and conduct the final inspection once the shed is up.
If you do need a planning permit, you have to lodge the application with your council prior to doing any building work. The statutory decision period for permitted applications is 28 days while that of Discretionary applications is 42 days because they are advertised for public comment.
Fees differ between each council, so check the cost directly with yours. More importantly, wait until the permit is in hand before you order the shed or begin construction.
Good plans can make the whole process smoother. With a well-illustrated engineering drawing and proper site plan, the planner or building surveyor gets all information needed without having to work from a rough sketch or ask further questions.
Once your approval is sorted, you can turn your attention to the site itself. Our guide on how to prepare your site explains what to do about levelling and the slab before construction starts.
How to check the rules for your property, and build council-ready
Before you order or build anything, you should consult PlanBuild Tasmania about zones and overlays and get the details verified from your local council. It is always better to do it even if you think that the shed will be exempted.
PlanBuild shows the zone, overlays and relevant codes for any Tasmanian address. From there, your council's planning team can tell you if any local rules or conditions also apply to the property.
The building side is easier when the shed is engineered from the start. Every Fair Dinkum Builds shed is engineered and code-compliant, with ShedSafe accreditation and a wind rating for your site. A 30-year system warranty sits behind each one. They're built from Australian steel, with COLORBOND® the finish most customers choose.
Our local Tasmanian experts deal with council approval requirements every week and will point you in the right direction for your property.
Ready to get moving? Browse our range of sheds or design your own with our Shed Designer App.
Frequently asked questions
Not always. When a shed comes under the planning exemption and meets the low risk building limits, it can be built without the need for a permit. In most residential properties, the planning maximum is 9m², while a rural property has a maximum of 108m² of total outbuildings. But you will still have to provide the Form 80 to the council once the shed is complete. And, since planning and construction are two different topics, you need to verify them separately.
Form 80 is the Notice of Low Risk Work. You or your builder submit it to your local council after Category 1 low risk building work is finished, allowing the council to update its property records. The form will be lodged once the building work is completed, together with the site plan and the required plans. It is a notification, not an approval process.
Not usually, provided it's a detached, non-habitable (Class 10a) shed sited 6 m or more from a habitable building. Sheds closer than 6 m to the house on bushfire-prone land, or sheds attached to a house, may need to be built to the site's BAL under AS 3959.
Yes, but only for low risk work. No owner-builder permit is required if you are building a shed on-site up to 18m² or a prefabricated shed up to 36m². The same rule applies to a prefabricated farm shed smaller than 200m². If the shed is bigger than these sizes, you will have to obtain either a licensed builder or an Owner Builder Class 10a permit from CBOS.
28 days for a Permitted application and 42 days for a Discretionary one. Discretionary applications are advertised, and neighbouring properties can make representations. The clock starts once the council accepts a complete application, so missing documents add time.
Yes. On rural land, planning can allow up to 108m² of outbuildings linked to a dwelling before a permit is required. There is also a separate exemption for buildings used directly for farming. Building limitations will be different, and a prefabricated farm shed that is less than 200m² is considered low-risk work. Once you go over that limit, a building surveyor needs to be involved.